Case study · Secondary steel, purlins and ridge frames
Varun Beverages, Kosi: purlins and ridge frames in 2.5 days after a vendor default
A key vendor defaulted while the Varun Beverages project at Kosi was in active execution, leaving the site short of purlins and ridge frames with work already under way.
We stepped in and delivered the secondary steel in 2.5 days, with every piece marked for its position on site, ready for direct installation. The project never stopped, and the consultant approved the material with zero rework.

The challenge
The Varun Beverages project at Kosi was in active execution when a key vendor defaulted. That created an emergency requirement for secondary steel components: the purlins and ridge frames.
Work on site was already under way. Any delay in getting the material could have stopped the project completely, left labour standing idle and caused schedule overruns.
What was at risk
- A complete project halt
- Labour standing idle
- Schedule overruns
How we handled it
MNF Metals stepped in immediately as a rapid-response execution partner and planned the job so the crew on site could install every piece directly, with no re-measurement and no coordination delays.
- Made within 2.5 daysWe manufactured the purlins and ridge frames within a lead time of 2.5 days.
- Marked for siteEvery purlin and ridge frame was marked for its place on site.
- Installed directlyThe marking meant the crew could fix the steel straight away, without measuring it again.
The result
- No project haltThe project kept going despite the vendor failure.
- Continuous site workExecution on site carried on without disruption.
- Approved, zero reworkThe consultant approved the material and none of it needed rework.
Why clients choose MNF
This job shows we can step in when a project hits a crisis at the execution stage and still deliver quickly and accurately, taking full responsibility for the result.
On large industrial projects where downtime is not an option, that makes us the backup partner clients trust to keep the work going.
Has a vendor stopped supplying mid-project? Send the drawings and what is already fixed, and we will tell you today whether we can match it.